News

Hinkley Point C Project Update

By | |

 

Despite being affected by the Covid-19 health crisis, Hinkley Point C has made significant progress in 2020 on site, in the design execution plans and on the manufacturing of equipment.

In this context, a detailed review of schedule and cost has been performed to estimate the impact of the pandemic so far. This review has concluded the following (1) :

The start of electricity generation from Unit 1 is now expected in June 2026, compared to end-2025 as initially announced in 2016.

The project completion costs are now estimated in the range of £2015 22 to 23bn (2) . As a consequence, the projected rate of return (IRR) for EDF is estimated between 7.1% and 7.2% (3) .

The risk of COD delay of Units 1 and 2 is maintained at respectively 15 and 9 months. The realisation of this risk would incur a potential additional cost in the order of £2015 0.7bn. In this case, the IRR for EDF would be reduced by 0.3%.

The project is focused on the objective to lift the Unit 1 dome at the end of 2022.

(1) The information enclosed in this press release assumes the ability to begin a ramp up back to normal site conditions from the second quarter of 2021.
(2) Reminder on the costs previously announced in the Press release of 25 September 2019: £2015 21.5 – 22.5bn. Costs net of operational action plans, in 2015 sterling, excluding interim interest and excluding forex effect versus the reference exchange rate for the project of 1 sterling = 1.23 euro. Costs are calculated by deflating estimated costs in nominal terms using the British Construction OPI for All New Work index.
(3) EDF equity IRR calculated at the exchange rate of 1 sterling = 1.13 euro and including the capped compensation mechanism in place between the project’s shareholders.Previous IRR of 7.6% – 7.8% was based on an exchange rate of 1 sterling = 1.15 euro.